The Missoulian featured an interview with Envirocon’s Milltown Project Director Matt Fein in a story on the near completion of sediment removal at the  Superfund site. 

"All that's left is what's under the rail spur," Fein told the Missoulian. Fein recently met with the governor to give him an update. More than 2.2 million cubic yards of contaminated sediment have been shipped from Milltown to ARCO’s repository at the Anaconda Superfund site. An additional 250,000 cubic yards will be excavated from the old Clark Fork river channel and be placed in an on-site repository.

Read the Missoulian article here.